Arts Council Project Grants budgets: how to build a realistic project budget

Live performance at Threes a Crowd, Abingdon Studios, Blackpool, 2021. Funded by Arts Council England.
A project budget has a habit of expanding just as you think you’ve finished it.
You remembered the artist fees and the venue. Then there’s transport, captioning, a technician, printing and the person who will spend three days sorting out everyone’s invoices.
Somewhere in there, you were supposed to get paid too.
A useful Arts Council Project Grants budget shows how the work will happen and what it will cost. It also gives you a chance to spot problems while they’re still relatively cheap to solve.
Here’s how we’d approach one.
Start with the work
Take your project plan and go through it stage by stage.
Who is doing the research? Who is making the work? Who installs it, promotes it, runs the events and writes the final report? What does each stage need?
Put a cost beside each job, resource and service. Start with a working spreadsheet where you can see your calculations, then transfer the figures into the application’s budget headings.
Keep the basis for each figure nearby: a quote, a fee agreement, a hire price or a calculation you can explain.
“Production: £3,000” will eventually need unpacking. Doing that now helps you find the missing costs.
Include your own fee
If you’re making the work and managing the project, account for both roles and the time each needs.
A fee for ten days might include eight days of making and two days of installation. Project management could involve a separate allocation for scheduling, booking, communication and reporting. Count each day once.
Use an appropriate rate for the work and your experience, informed by relevant sector guidance. ACE expects proper payment and fees that meet or exceed recognised guidance from the relevant lead bodies. artscouncil.org.uk
Preparation, research and planning take time. So do the emails. If you routinely describe those jobs as “just a bit of admin”, try timing them.
Agree fees and responsibilities with collaborators early. A realistic budget gives people a clear idea of what they’re being asked to do for the money.
Cost access while you can still plan for it
Think about what audiences and participants will need to experience the project. That might include captioning, interpretation, accessible formats or support with travel. Ask about actual requirements and get costs.
Personal access costs concern support that you or your core creative team need to deliver the project and manage the grant. ACE treats these separately from audience access and from support to prepare an application.
Its access guidance also explains how eligible personal access costs affect funding thresholds and match-funding calculations.
Use the current access guidance linked from ACE’s guidance library when entering these figures.
Make the small costs visible
Go back through the project looking for costs attached to practical decisions.
Transport may need a return journey. Installation might involve equipment hire. Printing could need delivery. A project with several venues might need more coordination than one person can reasonably absorb.
Check what supplier quotes include, including VAT, and establish the VAT treatment that applies to your project.
Include a proportionate contingency for unexpected costs, based on where prices or quantities could change. Explain how you’ve arrived at it.
A contingency has a job to do. It won’t repair a budget that leaves out half the installation.
A worked project budget
Here’s an invented example for a small exhibition with two public events. These figures demonstrate the calculations; choose fees and costs appropriate to your own project.
There are no personal access costs or contributions in kind in this example.
Expenditure | Calculation or basis | Cost |
Lead artist | 10 days × £300 | £3,000 |
Production and project management | 6 days × £300 | £1,800 |
Guest artists | 2 fees × £600 | £1,200 |
Space and equipment hire | Supplier quotes | £1,000 |
Materials and fabrication | Itemised estimate | £1,600 |
Audience access provision | Costed services | £1,000 |
Travel and transport | Route and delivery estimates | £600 |
Marketing and documentation | Agreed briefs and quotes | £1,000 |
Insurance and project overheads | Project-related costs | £300 |
Contingency | Allowance for identified uncertainties | £500 |
Total cash expenditure | £12,000 |
The income could look like this:
Cash income | Status in this example | Amount |
Arts Council grant requested | Applied for | £10,800 |
Partner contribution | Confirmed | £600 |
Event ticket sales | Forecast | £600 |
Total cash income | £12,000 |
The ticket forecast assumes two events, each with 40 places, selling 75% of capacity at £10 a ticket: 2 × 40 × 75% × £10 = £600.
That assumption still needs testing against what you know about your audience. Work out what you would do if sales were lower, and explain any significant risk.
Your own calculations may be completely different. The useful habit is being able to explain them.
Understand what counts as match funding
ACE asks applicants to try to secure at least 10% of the overall project cost from other sources, where possible. This can include partner contributions, earned income, donations, other grants and support in kind. Eligible personal access costs are excluded from the amount used for that calculation. artscouncil.org.uk
In the example above, the £600 partner contribution and £600 ticket forecast provide £1,200: 10% of the £12,000 cash project cost.
If you cannot secure 10%, use the application to explain your circumstances and what you’ve tried. ACE considers whether match funding should have been possible, so take this part seriously.
Keep confirmed and expected income clearly labelled. A promising conversation about sponsorship is a reason to follow up; it becomes confirmed income when someone commits to the contribution.
Keep cash and support in kind distinct
Support in kind means goods or services supplied free or at a discount that you would otherwise have needed to pay for.
If a partner provides a room that would normally cost £400 to hire, agree and record that value. It may help demonstrate their contribution to the project.
It still leaves you with £400 less cash than a £400 cash donation would.
Keep that distinction visible in your working budget. You need to know how much money will actually reach your account and which costs have already been covered through other arrangements.
For applications of £30,000 or under, the current guidance tells you to enter support in kind in the income table and leave it out of the expenditure table. Follow those instructions when completing the form.
Check when the money arrives
A project can have enough income overall and still run short midway through delivery.
Put expected payments and spending on a simple monthly timeline. Check ACE’s payment arrangements, when partners will transfer their contributions and when suppliers need paying.
Ticket income may arrive after production bills. A venue might need a deposit before you’ve received a partner’s contribution. Those gaps need a plan.
Also keep spending to prepare the application separate from the delivery budget. ACE cannot retrospectively fund costs incurred before its decision. Application access support has separate arrangements.
Read the application with the budget open
Check that everything you promise has time and money attached to it.
Four workshops need four workshops’ worth of preparation and delivery. An accessible film screening needs the access services you’ve described. Your explanation of who does the work should match the people being paid.
Then check the calculations, income assumptions and cash requirements.
If the figures only work when you remove your fee or assume every event sells out, revisit the scale and delivery plan. You need a project you can afford to finish.
Funding application reviews from Short Supply
If you’d like help checking your figures alongside the project plan, STACK THE ODDS offers individual Arts Council Project Grants application support.
Our Application Audit includes a budget and feasibility review. The Funding Sprint includes support developing your budget, timeline and wider project.
You can tell us what you’re planning through the enquiry form, and we’ll confirm which support fits.